• Accessibility page
  • Search skiplink
  • Main navigation skiplink
  • Main content skiplink
  • Utility Navigation skiplink
  • Contact NZTA
SmartMovez logo
NZTA logo
  • Give us feedback
  • Site help
  • Site map
  • Outcomes
  • Various topics
  • Activities
  • Planning & funding
  • Data
  • Web tools
  • References
  • About NZTA
Home Economic evaluation manual 2007- Volume 1, Amendment 1 (road infrastructure) Appendix 12 - Update factors and incremental BCR A12.4 - Target incremental BCR

References

  • Planning, programming and funding
  • Economic evaluation
  • Procurement

A12.4 - Target incremental BCR

  • A12.1 - Update factors and incremental BCR
  • A12.2 - Update factors for construction and maintenance costs
  • A12.3 - Update factors for benefits
  • A12.4 - Target incremental BCR

A12.4 - Target incremental BCR

Target incremental BCR

The analyst shall choose and report the target incremental BCR used when undertaking incremental analysis of project options. Where the selected target incremental ratio differs to the guidance below, the analyst must provide a detailed explanation supporting the chosen value. The following guidance is provided:

  1. The minimum incremental BCR shall be 1.0, in order to ensure that a higher cost project option is more efficient than a lower cost option.
  2. Where the BCR of the preferred option is greater than 2.0 but less than 4.0, the target incremental BCR shall be 2.0.
  3. Where the BCR of the preferred option is greater than or equal to 4.0, the target incremental BCR shall be 4.0.